Carhartt Indiana

Greenwood, IN

Synergy Construction completed an interior build-out of a Carhartt store in the Greenwood Park Mall in Indianapolis, Indiana. In order to avoid disruption of the mall we completed the removal of the existing façade and installed new materials all after hours. Synergy completed this project in two months.

Project in BriefInterior Build-out of retail space

Project Duration
2 Months

Budget

$350,000

Size
3,400 SF

Team
Synergy Construction Group
RGLA